We’ve been making the case that data centers should pay the full cost of the power infrastructure they require, rather than shifting those expenses onto regular residential customers like what is happening now.
Analysis: APS customers paid $587 million for data center sector growth. APS denies claim. 12News
Southwest Gas’s latest rate request raises a related question: Should existing customers pay to extend gas infrastructure to serve new development?
Our answer is the same: Growth should pay its own way.
Southwest Gas is asking the Arizona Corporation Commission for approximately $101 million in additional annual revenue. The company estimates its proposal would increase the average residential customer’s bill by a whopping 10.69%, following its most recent Arizona rate adjustment in March 2025.
Why This Is a Public Health Issue
Affordable energy helps families maintain safe homes, prepare meals, and meet basic needs. When utility bills rise, less money remains for food, housing, prescriptions, and healthcare.
Families may delay medical appointments, put off filling prescriptions, or cut back on nutritious food. Financial strain also creates stress and can threaten housing stability.
These pressures fall hardest on people with low incomes, older adults on fixed incomes, and people with disabilities or chronic illnesses. The Commission should consider the combined burden of gas, electricity, water, and other essential expenses—not just each proposed increase separately.
Who Benefits? Who Pays?
Safe and reliable utility service requires investment. But spending money doesn’t automatically establish that existing customers should pay.
The Commission should distinguish necessary maintenance and safety improvements from infrastructure built to serve new development. Developers should cover the full incremental cost of extending gas service to their projects.
The same principle applies to data centers. If a giant new customer requires more generating capacity, substations, or transmission lines, that customer should pay the costs it creates. Residential customers shouldn’t subsidize infrastructure built primarily to help someone else.
Whether we’re talking about gas pipelines or electricity generation, regulators need to ask: Who needs this investment, who benefits, and who should pay?
Preserve Public Oversight
Southwest Gas also proposes an annual rate-adjustment mechanism to recover changes in its cost of service. We’re concerned that these “formula rates” would weaken the scrutiny and meaningful public participation a full rate case provides.
Customers deserve opportunities to question spending and explain how increases affect their lives. Their household budgets deserve as much attention as the utility’s financial needs.
AzPHA is urging the Commission to deny this request, reject formula rates, and require developers to pay their own infrastructure costs.
You can send a public comment to the Arizona Corporation Commission. Reference Southwest Gas Docket G-01551A-26-0018.
See the letter that we sent to the Corporation Commission docket for this case: SW-Gas-Rate-Case-Comments-